CONSTRUCTION MANAGEMENT AGREEMENT
BY AND BETWEEN
NYU HOSPITALS CENTER
- OWNER -
AND
____________________
- CONSTRUCTION MANAGER -
-------------
PROJECT
________________________
DATED AS OF
_______________
CONTENTS
ARTICLE CAPTION PAGE
I CONTRACT DOCUMENTS .................................................................... 1
II SCOPE OF THE WORK ........................................................................... 2
III CONSTRUCTION MANAGER’S STATUS AND DUTIES ................... 2
IV OWNER'S RESPONSIBILITIES ............................................................ 17
V TIME REQUIREMENTS AND DELAY ................................................ 18
VI PRECONSTRUCTION FEE .................................................................. 20
VII COSTS OF THE WORK ........................................................................ 20
VIII COSTS NOT TO BE REIMBURSED ..................................................... 22
IX CONSTRUCTION FEE .......................................................................... 23
X CHANGES IN THE WORK AND CHANGE ORDERS ....................... 23
XI PAYMENTS ............................................................................................ 27
XII INSURANCE ........................................................................................... 32
XIII LIENS AND OTHER ENCUMBRANCES ............................................ 37
XIV PROCEEDING WITH THE WORK ........................................................ 37
XV NOTICE OF CLAIM ................................................................................ 37
XVI CORRECTION AND REMOVAL OF WORK ...................................... 39
XVII WARRANTY .......................................................................................... 39
XVIII TERMINATION ....................................................................................... 39
XIX ASSIGNMENTS ...................................................................................... 41
XX ENTIRE AGREEMENT ........................................................................... 42
XXI BOOKS AND RECORDS ....................................................................... 42
XXII INDEMNIFICATION .............................................................................. 43
XXIII ADDITIONAL PROVISIONS ................................................................ 44
i
EXHIBITS
EXHIBIT A - PROJECT DESCRIPTION
EXHIBIT B - PRELIMINARY LIST OF GENERAL CONDITIONS WORK ITEMS
EXHIBIT C - LIST OF CONSTRUCTION MANAGER’S PROJECT PERSONNEL
EXHIBIT D - STANDARD SUBCONTRACT FORMS
EXHIBIT E - FORM OF GMP/SCHEDULE AMENDMENT
EXHIBIT F - FINAL PAYMENT CERTIFICATE, RELEASE AND LIEN WAIVER FORMS
EXHIBIT G - OWNER’S WORK POLICIES AND PROCEDURES
EXHIBIT H - OWNER'S STATEMENT OF POLICY REGARDING REIMBURSEMENT OF
COSTS UNDER COST REIMBURSABLE CONSTRUCTION CONTRACTS
EXHIBIT I - FEMA ADDENDUM #1 - CONSTRUCTION
EXHIBIT J - FORM OF PAYMENT AND PERFORMANCE BONDS
DEFINITIONS
Term Provision
Allowance 3.3(d)(i)
Architect Recital
Change Order 10.4
Construction Fee 9.1, GMP/Schedule Amendment
Construction Manager Preamble
Construction Schedule 3.3(a), GMP/Schedule Amendment
Contingency 3.3(e), 7.2.2, GMP/Schedule Amendment
Contract Documents 1.1
Contract Time 5.1
Costs of the Work 7.1
Direct Personnel Expense 7.2.1(b)(ii)
FEMA Addendum #1 - Contracting 23.18, Exhibit I
Final List of General Conditions Work Items 3.4
Final Payment Certificate and Release and
Lien Waiver 11.1.8, Exhibit F
General Conditions Amount 7.2.1(b)
General Conditions Work 3.4
Guaranteed Maximum Price (GMP) 3.3(a), 3.7, GMP/Schedule Amendment
GMP/Schedule Amendment 3.3(k)
GMP/Schedule Submission 3.3(a)
Hold 3.3(d)(ii)
Indemnified Parties 22.1
Insurance Specifications 12.6
Medical Center Recital
OCIP 12.3.6
Owner Preamble
Owner’s Work 5.3
Owner’s Work Policies and Procedures 3.8(hh), Exhibit G
Preconstruction Fee Article 6
Preliminary List of General Conditions
Work Items 3.4
Project Recital, 2.1, Exhibit A
Punch Lists 3.8(w)
Punch List Work 5.2(c)
Requisition 11.1.1
Senior Staff 3.12.1
Site Recital
Site Labor 3.4
Statement of Policy Article 1, Exhibit H
Subcontract 3.4(a)
no reviews yet