NEC 3 The Accepted Programme
Submitting and revising the Accepted Programme Clause 31 and 32 NEC3 The programme
identified in the
Contract Data is the
When must the Contractor submit a programme ? Is there a programme identified in Yes “Accepted Programme”
the contract data ?
NEC 3 Clause 31.2 The Contractor Must submit a
first programme for acceptance to the Project No Has the Project Manager instructed Contractor to When should the
Manager, within the period stated in the submit a revised Programme contractor revise
Contract Data the accepted
Programme?
Has the Contractor Yes No
NEC 3 Clause 31.2 submitted the first
The programme submitted Mustshow: programme for
acceptance showing Contractor must
The starting date, access dates, key dates all the information submit a revised Even if there is no instruction the
and completion date. required ? programme within contractor must submit a revised
Planned completion this period for reply programme on a periodic basis. The
The period for reply is max interval between programmes
Order / timing of operations set out in contract being submitted is set out in the
Order / timing of work the employer and No data part 1 contract data part 1
any others, and the dates when the
contractor plans to complete work required Yes
to allow others to carry out works 25% of payment
The dates when the contractor plans to withheld until a Contractor Submits a Revised Programme to the Project
meet each condition stated for the key correct Manager
dates programme is
Dates when the Contractor needs access to submitted
part, of the site if later than its access dates
Acceptances, plant, materials and other Has the Project Manager accepted the programme or notified
things to be provided by the employer and reasons for not accepting within 2 weeks
information from others Yes There is an “Accepted Programme “
For each operation, a statement of how the No
contractor pans to do the work (including Contractor to revise and issue
equipment and resources) Project Manager Does Project Manager Accepts
Provisions for Float, Time risk allowances, Neither the programme contractually compliant
Health and safety requirements, contract programme
procedures, information showing how each Project manager notifies Yes
activity on the activity schedule relates to Contractor notifies a reason for not accepting Contractor notifies and
operation when using Option A or Option C compensation event the programme. Is the compensation event under
under Clause 60.1(6) reason listed in Clause 31.3 No clause 60.1(9)