sheet 1 project cost summary project old north church crypt restoration park boston national historical park park alpha bost pmis number 232488 basic requirement total direct costs a10 foundations a20 ...

icon picture XLSX Filetype Excel XLSX | Posted on 14 Aug 2022 | 3 years ago
Partial file snippet.
Sheet 1: Project Cost Summary
Project: Old North Church Crypt Restoration
























Park: Boston National Historical Park
















































Park Alpha: BOST
























PMIS Number: 232488


















































































BASIC REQUIREMENT
Total Direct Costs
























A10 Foundations
$-
























A20 Basement Construction
$-
























B20 Exterior Enclosure
$-
























C10 Interior Construction
$-
























C30 Interior Finishes
$-
























D20 Plumbing
$-
























D30 HVAC
$-
























D50 Electrical
$-
























F10 Special Construction
$-
























F20 Selective Building Demolition
$-
























G20 Site Improvements
$-
























G30 Site Mechanical Utilities
$-

























Total Direct Construction Costs
$-

























General Conditions
$-

























Subtotal NET Construction Cost
$-

























Bonds & Permitting & Insurance 0.00% $-

























Overhead 0.00% $-

























Profit 0.00% $-

























Subtotal Bonds, Permit, O&H
$-

























Total Cost of Basic Requirement
$-



















































































OPTION 1 - Exterior Construction and Ramp
Total Direct Costs

























Option 1
$-

























Total Direct Construction Costs
$-

























General Conditions
$-

























Subtotal NET Construction Cost
$-

























Bonds & Permitting & Insurance 0.00% $-

























Overhead 0.00% $-

























Profit 0.00% $-

























Subtotal Bonds, Permit, O&H
$-

























Total Cost of Additive 1
$-



















































































OPTION 2 - Ticket Booth Relocation
Total Direct Costs

























Option 2
$-

























Total Direct Construction Costs
$-

























General Conditions
$-

























Subtotal NET Construction Cost
$-

























Bonds & Permitting & Insurance 0.00% $-

























Overhead 0.00% $-

























Profit 0.00% $-

























Subtotal Bonds, Permit, O&H
$-

























Total Cost of Additive 2
$-

























Sheet 2: A10 Foundations
Project: Old North Church Crypt Restoration










Park: Boston National Historical Park










Park Alpha: BOST










PMIS: 232488
























Summary Item: A10 Foundations





















Uniformat II WBS Code Description Quantity Unit MATERIAL LABOR EQUIPMENT TOTALS
Material Cost/Unit Total Material Cost Labor Cost/Unit Total Labor Cost Equipment Cost/Unit Total Equipment Cost Total Cost/Unit Total Cost

A1030
SLAB ON GRADE









Basic 03.30.00 Furnish concrete material (incl. waste) 4 cy $- $0 $- $0 $- $0 $- $0
Basic 03.22.00 Furnish & install wire mesh reinforcement 217 sf $- $0 $- $0 $- $0 $- $0
Basic 03.30.00 Place & finish 5" slab on grade 217 sf $- $0 $- $0 $- $0 $- $0
Basic 03.30.00 Allowance for details at tie-in of new to existing 1 ls $- $0 $- $0 $- $0 $- $0
Basic 03.30.00 Concrete steps at landing (2 steps) 1 ls $- $0 $- $0 $- $0 $- $0
Basic 07.26.00 Vapor barrier below slab 217 sf $- $0 $- $0 $- $0 $- $0
Basic 03.30.00 Concrete pump 1 day $- $0 $- $0 $- $0 $- $0
Basic 03.30.00 Supervision/foreman 2 day $- $0 $- $0 $- $0 $- $0
Basic 31.23.00 Allowance for sump pump pit 1 ls $- $0 $- $0 $- $0 $- $0


























SUBTOTAL SLAB ON GRADE


$0
$0
$0
$0
Summary Item:
A10 Foundations









Uniformat II WBS Code Description Quantity Unit MATERIAL LABOR EQUIPMENT TOTALS
Material Cost/Unit Total Material Cost Labor Cost/Unit Total Labor Cost Equipment Cost/Unit Total Equipment Cost Total Cost/Unit Total Cost



Basic Requirement








$0



Option 1








$0.00



Option 2








$0.00














A10 Foundations
$0

The words contained in this file might help you see if this file matches what you are looking for:

...Sheet project cost summary old north church crypt restoration park boston national historical alpha bost pmis number basic requirement total direct costs a foundations basement construction b exterior enclosure c interior finishes d plumbing hvac electrical f special selective building demolition g site improvements mechanical utilities general conditions subtotal net bonds amp permitting insurance overhead profit permit o h of option and ramp additive ticket booth relocation item uniformat ii wbs code description quantity unit material labor equipment totals costunit slab on grade furnish concrete incl waste cy install wire mesh reinforcement sf place finish quot allowance for details at tiein new to existing ls steps landing vapor barrier below pump day supervisionforeman sump pit...

no reviews yet
Please Login to review.