418x Filetype XLSX File size 0.36 MB Source: www1.nyc.gov
Revision 18. Date February 18, 2022. This is a version controlled document. Printed copies are not controlled
Cost Estimate Submission Checklist
Project ID:
Project Name:
Checklist Item Reference Included For DDC Use
(Y/N)
Estimating Workshop Minutes of Meeting 1
Construction Work Cost Summary Worksheet
Detailed Worksheets
Hard Cost Detail Worksheet (Level 1)
Hard Cost Detail Worksheet (Level 2)
Hard Cost Itemized General Requirements Worksheet
Bid Contingency Worksheet
Construction Contract Allowance Worksheet
Basis of Estimate
Report
Project Complexity Report
Project Type Report
1. Minutes of Meeting shall include all decisions made relevant to basis of estimate
Note:
Shaded cell is where data must be entered
08/14/2022 Section 3.2. SubmissionChecklist 272
Project ID: Construction Work Cost Summary
Line Item Description Calculation Cost
A Hard Cost Summary see Detail Sheet $ -
B General Conditions Included in Hard Cost, General Requirements (Division 1)
C Design Contingency see Basis of Estimate
D Overhead and Profit see Basis of Estimate
E Cost Escalation see Basis of Estimate
F Subtotal Sum (A thru E) $ -
G Bid Contingency see Detail Sheet $ -
H Construction Contract Allowance see Detail Sheet $ -
I Estimated Construction Cost at Award F+G+H $ -
J Construction Contingency see Basis of Estimate
K Estimated Construction Cost at Completion I+J $ -
SIGN OFF:
PROJECT MANAGER: SIGNATURE: DATE:
UNIT PROGRAM DIRECTOR: SIGNATURE: DATE:
08/14/2022 Section 3.2. CostSummary 272
Project ID: Hard Cost Estimate (Level 1)
Trade Cost %
General Construction (Including General Condition) $ -
Plumbing $ -
DDC - Bid Disposition Use Only
Mechanical $ -
Electrical $ -
Subtotal $ -
Total cost
CSI Division: Total Cost
Material: Labor: Equipment:
DIVISION 01 - GENERAL REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS $ - $ - $ - $ -
DIVISION 03 - CONCRETE $ - $ - $ - $ -
DIVISION 04 - MASONRY $ - $ - $ - $ -
DIVISION 05 - METALS $ - $ - $ - $ -
DIVISION 06 - WOOD, PLASTICS, COMPOSITES $ - $ - $ - $ -
DIVISION 07 - THERMAL AND MOISTURE PROTECTION $ - $ - $ - $ -
DIVISION 08 - OPENINGS $ - $ - $ - $ -
DIVISION 09 - FINISHES $ - $ - $ - $ -
DIVISION 10 - SPECIALTIES $ - $ - $ - $ -
DIVISION 11 - EQUIPMENT $ - $ - $ - $ -
DIVISION 12 - FURNISHINGS $ - $ - $ - $ -
DIVISION 13 - SPECIAL CONSTRUCTION $ - $ - $ - $ -
DIVISION 14 - CONVEYING EQUIPMENT $ - $ - $ - $ -
DIVISION 21 - FIRE SUPPRESSION $ - $ - $ - $ -
DIVISION 22 - PLUMBING $ - $ - $ - $ -
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) $ - $ - $ - $ -
DIVISION 25 - INTEGRATED AUTOMATION $ - $ - $ - $ -
DIVISION 26 - ELECTRICAL $ - $ - $ - $ -
DIVISION 27 - COMMUNICATIONS $ - $ - $ - $ -
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY $ - $ - $ - $ -
DIVISION 31 - EARTHWORK $ - $ - $ - $ -
DIVISION 32 - EXTERIOR IMPROVEMENTS $ - $ - $ - $ -
DIVISION 33 - UTILITIES $ - $ - $ - $ -
DIVISION 34 - TRANSPORTATION $ - $ - $ - $ -
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION $ - $ - $ - $ -
DIVISION 40 - PROCESS INTEGRATION $ - $ - $ - $ -
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT $ - $ - $ - $ -
DIVISION 42 - PROCESS HEATING, COOLING, AND DRYING EQUIPMENT $ - $ - $ - $ -
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT $ - $ - $ - $ -
DIVISION 44 - POLLUTION AND WASTE CONTROL EQUIPMENT $ - $ - $ - $ -
DIVISION 45 - INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT $ - $ - $ - $ -
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT $ - $ - $ - $ -
DIVISION 48 - ELECTRICAL POWER GENERATION $ - $ - $ - $ -
Hard Cost: $ - $ - $ - $ -
Hard Cost Summary(Including General Requirement): $ -
08/14/2022 Section 3.2. HardCostDetailLevel1 272
Project ID: Hard Cost Estimate (Level 2)
Sub Work CSI Sub RSMeans Vendor Quote Material $: Labor $: Equipment $: Total $:
No. (*) CSI Division: Division: 12-digit item (Yes/ No): Description: Qty Unit: DDC COMMENTS:
code: U/Cost: T/Cost: U/Time: T/Time: Wage: U/Cost: T/Cost: U/Cost: T/Cost: U/Cost: T/Cost:
DIVISION 01 - GENERAL REQUIREMENTS
Total from HardCostGeneralRequirements $ -
DIVISION 01 - GENERAL REQUIREMENTS SUB TOTAL
DIVISION 02 - EXISTING CONDITIONS
copy above cell and insert copied cell above the row
DIVISION 02 - EXISTING CONDITIONS SUB TOTAL
DIVISION 03 - CONCRETE
copy above cell and insert copied cell above the row
DIVISION 03 - CONCRETE SUB TOTAL
DIVISION 04 - MASONRY
copy above cell and insert copied cell above the row
DIVISION 04 - MASONRY SUB TOTAL
DIVISION 05 - METALS
copy above cell and insert copied cell above the row
DIVISION 05 - METALS SUB TOTAL
DIVISION 06 - WOOD, PLASTICS, COMPOSITES
copy above cell and insert copied cell above the row
DIVISION 06 - WOOD, PLASTICS, COMPOSITES SUB TOTAL
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
copy above cell and insert copied cell above the row
DIVISION 07 - THERMAL AND MOISTURE PROTECTION SUB TOTAL
DIVISION 08 - OPENINGS
copy above cell and insert copied cell above the row
DIVISION 08 - OPENINGS SUB TOTAL
DIVISION 09 - FINISHES
copy above cell and insert copied cell above the row
DIVISION 09 - FINISHES SUB TOTAL
DIVISION 10 - SPECIALTIES
copy above cell and insert copied cell above the row
DIVISION 10 - SPECIALTIES SUB TOTAL
08/14/2022 Page 4 of 272 Section 3.2. HardCostDetailLevel2
no reviews yet
Please Login to review.