345x Filetype XLSX File size 0.05 MB Source: www.ezview.wa.gov
Sheet 1: ProjectSchedule
| HFC End-of-life Management Program Project Schedule | ||||||||||||||||||||||||||||||||||||||||||
| Last updated: July 12, 2021 | Completed ahead of schedule | Completed on time | Completed late | Task in progress | Task scheduled | Task overdue | ||||||||||||||||||||||||||||||||||||
| May | June | July | August | September | October | November | December | |||||||||||||||||||||||||||||||||||
| TASK | TASK LEAD |
PLANNED START | PLANNED END | EXPECTED DURATION | ACTUAL START | ACTUAL END | ACTUAL DURATION | PROGRESS | 5/17 | 5/24 | 5/31 | 6/7 | 6/14 | 6/21 | 6/28 | 7/5 | 7/12 | 7/19 | 7/26 | 8/2 | 8/9 | 8/16 | 8/26 | 8/30 | 9/6 | 9/13 | 9/20 | 9/27 | 10/4 | 10/11 | 10/18 | 10/25 | 11/1 | 11/8 | 11/15 | 11/22 | 11/29 | 12/6 | 12/13 | 12/20 | 12/27 | |
| Project Development | ||||||||||||||||||||||||||||||||||||||||||
| Develop project plan | Kimberly | 5/17/21 | 5/21/21 | 5 | 5/17/21 | 5/21/21 | 5 | 100% | ||||||||||||||||||||||||||||||||||
| Identify deliverables | Kimberly | 5/17/21 | 5/21/21 | 5 | 5/17/21 | 5/21/21 | 5 | 100% | ||||||||||||||||||||||||||||||||||
| Identify team members | Program Managers | 5/17/21 | 5/24/21 | 8 | 5/21/21 | 5/24/21 | 4 | 100% | ||||||||||||||||||||||||||||||||||
| Develop roles and responsibilities | Kimberly | 5/17/21 | 6/4/21 | 19 | 5/17/21 | 5/24/21 | 8 | 100% | ||||||||||||||||||||||||||||||||||
| Develop preliminary timeline | Kimberly | 5/17/21 | 5/21/21 | 5 | 5/17/21 | 5/21/21 | 5 | 100% | ||||||||||||||||||||||||||||||||||
| Develop and finalize team charter | Kimberly | 5/17/21 | 6/4/21 | 19 | 5/17/21 | 5/24/21 | 8 | 100% | ||||||||||||||||||||||||||||||||||
| Finalize roles and responsibilities | Kimberly | 5/17/21 | 6/4/21 | 19 | 5/17/21 | 5/24/21 | 8 | 100% | ||||||||||||||||||||||||||||||||||
| Finalize overall project plan | Kimberly | 5/17/21 | 6/4/21 | 19 | 5/17/21 | 5/24/21 | 8 | 100% | ||||||||||||||||||||||||||||||||||
| Program Managers meeting | Program Managers | 5/24/21 | 5/24/21 | 1 | 5/24/21 | 5/24/21 | 1 | 100% | ||||||||||||||||||||||||||||||||||
| Monthly Program Managers check-in scheduled | Kimberly | 5/24/21 | 6/8/21 | 16 | 5/24/21 | 6/8/21 | 16 | 100% | ||||||||||||||||||||||||||||||||||
| Establish SharePoint site | Laura W. | 5/24/21 | 6/15/21 | 23 | 6/1/21 | 6/14/21 | 14 | 100% | ||||||||||||||||||||||||||||||||||
| Weekly team planning meeting established | Kimberly | 5/24/21 | 5/27/21 | 4 | 5/24/21 | 6/3/21 | 11 | 100% | ||||||||||||||||||||||||||||||||||
| Coordinate with rulemaking team to finalize scope of recommendations | Kimberly | 5/24/21 | 6/10/21 | 18 | 6/7/21 | 0 | 100% | |||||||||||||||||||||||||||||||||||
| Tribal consultation/outreach discussion | Kimberly | 6/1/21 | 6/18/21 | 18 | 6/16/21 | 6/16/21 | 1 | 100% | ||||||||||||||||||||||||||||||||||
| Tribal consultation/outreach follow-up | Kimberly | 7/26/21 | 8/13/21 | 19 | 0 | |||||||||||||||||||||||||||||||||||||
| Stakeholder Engagement | ||||||||||||||||||||||||||||||||||||||||||
| Identify known key stakeholders to solicit feedback | Kimberly | 6/3/21 | 6/15/21 | 13 | 6/1/21 | 0 | 100% | |||||||||||||||||||||||||||||||||||
| Engage in personal communication to invite participation by key stakeholders | Kimberly | 6/7/21 | 7/21/21 | 45 | 6/7/21 | 0 | 75% | |||||||||||||||||||||||||||||||||||
| Research/identify other new potential stakeholders, including local government | Kimberly | 6/7/21 | 7/21/21 | 45 | 6/7/21 | 0 | 80% | |||||||||||||||||||||||||||||||||||
| Engage in personal communication to invite participation by new stakeholders | Kimberly | 6/7/21 | 7/21/21 | 45 | 6/2/21 | 0 | 80% | |||||||||||||||||||||||||||||||||||
| Launch eComments site | Kimberly | 6/7/21 | 6/10/21 | 4 | 6/7/21 | 6/14/21 | 8 | 100% | ||||||||||||||||||||||||||||||||||
| Launch EZView page | Kimberly | 6/8/21 | 6/14/21 | 7 | 6/8/21 | 6/11/21 | 4 | 100% | ||||||||||||||||||||||||||||||||||
| Prepare webinar/eComments announcements | Kimberly | 6/7/21 | 6/11/21 | 5 | 6/8/21 | 6/11/21 | 4 | 100% | ||||||||||||||||||||||||||||||||||
| Develop schedule informational document / Gantt chart for posting on EZView page | Kimberly | 6/14/21 | 6/25/21 | 12 | 6/8/21 | 0 | 80% | |||||||||||||||||||||||||||||||||||
| Schedule webinars | Kimberly | 6/7/21 | 6/9/21 | 3 | 6/8/21 | 6/8/21 | 1 | 100% | ||||||||||||||||||||||||||||||||||
| Send webinar announcement to listserv | Linda | 6/14/21 | 6/18/21 | 5 | 6/8/21 | 6/11/21 | 4 | 100% | ||||||||||||||||||||||||||||||||||
| Hold Webinar #1 | Kimberly | 6/30/21 | 6/30/21 | 1 | 0 | 100% | ||||||||||||||||||||||||||||||||||||
| Hold Webinar #2 | Kimberly | 7/9/21 | 7/9/21 | 1 | 0 | 100% | ||||||||||||||||||||||||||||||||||||
| On-going stakeholder engagement | TBD | 12/1/21 | 1/10/22 | 41 | 5/17/21 | 7/21/21 | 75% | |||||||||||||||||||||||||||||||||||
| Additional Research | ||||||||||||||||||||||||||||||||||||||||||
| Review Don't Drip and Drive Program reports for insight on older vehicles | Kimberly | 6/7/21 | 6/18/21 | 12 | 6/10/21 | 6/14/21 | 5 | 100% | ||||||||||||||||||||||||||||||||||
| Research re cost of replacement refrigerants | Abbey | 6/14/21 | 7/23/21 | 40 | 0 | 10% | ||||||||||||||||||||||||||||||||||||
| Research re cost of switching to replacements, including new or replacement equipment if needed | Abbey | 6/14/21 | 7/24/21 | 41 | 0 | 10% | ||||||||||||||||||||||||||||||||||||
| Research re cost of recycling old refrigerants and equipment or disposal and why one or the other | Megan | 6/14/21 | 7/25/21 | 42 | 0 | 75% | ||||||||||||||||||||||||||||||||||||
| Research current market incentives in Washington | Megan | 6/14/21 | 7/26/21 | 43 | 0 | 75% | ||||||||||||||||||||||||||||||||||||
| Research current market incentives in other jurisdictions | Megan | 6/14/21 | 7/27/21 | 44 | 0 | 75% | ||||||||||||||||||||||||||||||||||||
| Research funding options and financial assurance applicability | Kimberly | 6/14/21 | 7/28/21 | 45 | 0 | 40% | ||||||||||||||||||||||||||||||||||||
| Policy Decisions | ||||||||||||||||||||||||||||||||||||||||||
| Brief management about proposed legislative options (may need to be by email) | Kimberly | 7/9/21 | 7/12/21 | 4 | 0 | |||||||||||||||||||||||||||||||||||||
| Get decision on whether project will (1) make recommendations only or (2) develop bill language | Management Team | 7/12/21 | 7/16/21 | 5 | 0 | |||||||||||||||||||||||||||||||||||||
| Report | ||||||||||||||||||||||||||||||||||||||||||
| Begin drafting report and recommendations | Kimberly | 7/6/21 | 7/23/21 | 18 | 0 | 0% | ||||||||||||||||||||||||||||||||||||
| Summarize stakeholder feedback | Kimberly | 7/16/21 | 8/2/21 | 18 | 0 | 0% | ||||||||||||||||||||||||||||||||||||
| Begin incorporating stakeholder feedback into draft report | Kimberly | 8/2/21 | 8/13/21 | 12 | 0 | 0% | ||||||||||||||||||||||||||||||||||||
| Target date for finished first draft | Kimberly | 8/13/21 | 8/16/21 | 4 | 0 | |||||||||||||||||||||||||||||||||||||
| First round of internal review and edits | Peer reviewers | 8/16/21 | 8/27/21 | 12 | 0 | |||||||||||||||||||||||||||||||||||||
| Incorporate edits and prepare review draft | Kimberly | 8/30/21 | 9/3/21 | 5 | 0 | |||||||||||||||||||||||||||||||||||||
| Draft review by Program Managers | Program Managers | 9/7/21 | 9/17/21 | 11 | 0 | |||||||||||||||||||||||||||||||||||||
| Incorporate edits and prepare revised draft | Kimberly | 9/20/21 | 10/1/21 | 12 | 0 | |||||||||||||||||||||||||||||||||||||
| Complete proposed final report and recommendations | Kimberly | 10/1/21 | 10/1/21 | 1 | 0 | |||||||||||||||||||||||||||||||||||||
| Program "fatal flaw only" review | Program reviewers | 10/4/21 | 10/8/21 | 5 | 0 | |||||||||||||||||||||||||||||||||||||
| Submit final draft for Gov Relations review | Kimberly | 10/11/21 | 10/11/21 | 1 | 0 | |||||||||||||||||||||||||||||||||||||
| Government Relation review | GR Staff | 10/11/21 | 10/29/21 | 19 | 0 | |||||||||||||||||||||||||||||||||||||
| Make Government Relations-requested edits | Kimberly | 11/1/21 | 11/5/21 | 5 | 0 | |||||||||||||||||||||||||||||||||||||
| Submit final for Executive review | Kimberly | 11/8/21 | 11/8/21 | 1 | 0 | |||||||||||||||||||||||||||||||||||||
| Executive review | Executive Staff | 11/8/21 | 11/29/21 | 22 | 0 | |||||||||||||||||||||||||||||||||||||
| Make any final edits from Executive review | Kimberly | 11/29/21 | 11/30/21 | 2 | 0 | |||||||||||||||||||||||||||||||||||||
| Submit final report and recommendations (and bill language, if applicable) to Legislature | Kimberly | 12/1/21 | 12/1/21 | 1 | 0 | |||||||||||||||||||||||||||||||||||||
| Activity 1: Project Development | |||||
| Develop project plan | Complete | 5/17/21 | 5/21/21 | 100% | |
| Identify deliverables | Complete | 5/17/21 | 5/21/21 | 100% | |
| Identify team members | Complete | 5/24/21 | 5/21/21 | 100% | |
| Develop roles and responsibilities | Complete | 5/17/21 | 6/4/21 | 100% | |
| Develop preliminary timeline | Complete | 5/17/21 | 5/21/21 | 100% | |
| Develop and finalize team charter | Complete | 5/17/21 | 6/4/21 | 100% | |
| Finalize roles and responsibilities | Complete | 5/17/21 | 6/4/21 | 100% | |
| Finalize overall project plan | Complete | 5/17/21 | 6/4/21 | 100% | |
| Program Managers meeting | Complete | 5/24/21 | 5/24/21 | 100% | |
| Monthly Program Managers check-in scheduled | Complete | 5/24/21 | 6/8/21 | 100% | |
| Establish SharePoint site | In Progress | 5/24/21 | 6/15/21 | 75% | |
| Weekly team planning meeting established | Complete | 5/24/21 | 5/27/21 | 100% | |
| Coordinate with rulemaking team to finalize scope of recommendations | In Progress | 5/24/21 | 6/10/21 | 50% | |
| Tribal consultation/outreach discussion | Deferred | 6/1/21 | 6/15/21 | 0% | |
| Activity 2: Stakeholder Engagement | |||||
| Identify known key stakeholders to solicit feedback | In Progress | 6/3/21 | 6/15/21 | 50% | |
| Engage in personal communication to invite participation by key stakeholders | In Progress | 6/7/21 | 7/21/21 | 0% | |
| Research/identify other new potential stakeholders, including local government | Not Started | 6/7/21 | 7/21/21 | 0% | |
| Engage in personal communication to invite participation by new stakeholders | Not Started | 6/7/21 | 7/21/21 | 0% | |
| Launch eComments site | In Progress | 6/7/21 | 6/10/21 | 50% | |
| Launch EZView page | In Progress | 6/8/21 | 6/14/21 | 50% | |
| Prepare webinar/eComments announcements | In Progress | 6/7/21 | 6/11/21 | 50% | |
| Schedule webinars | Complete | 6/7/21 | 6/9/21 | 100% | |
| Hold Webinar #1 | Not Started | 6/30/21 | 6/30/21 | 0% | |
| Hold Webinar #2 | Not Started | 7/9/21 | 7/9/21 | 0% | |
| Activity 3: Additional Research | |||||
| Review Don't Drip and Drive Program reports for insight on older vehicles | Not Started | 6/7/21 | 6/18/21 | 0% | |
| Research re cost of replacement refrigerants | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Research re cost of switching to replacements, including new or replacement equipment if needed | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Research re cost of recycling old refrigerants and equipment or disposal and why one or the other | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Research current market incentives in Washington | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Research current market incentives in other jurisdictions | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Research funding options and financial assurance applicability | Not Started | 6/14/21 | 6/25/21 | 0% | |
| Activity 4: Policy Decisions | |||||
| Brief management about proposed legislative options (may need to be by email) | Not Started | 7/9/21 | 7/12/21 | 0% | |
| Get decision on whether project will (1) make recommendations only or (2) develop bill language | Not Started | 7/12/21 | 7/16/21 | 0% | |
| Activity 5: Report | |||||
| Begin drafting report and recommendations | Not Started | 7/6/21 | 7/16/21 | 0% | |
| Summarize stakeholder feedback | Not Started | 7/16/21 | 8/2/21 | 0% | |
| Begin incorporating stakeholder feedback into draft report | Not Started | 8/2/21 | 8/13/21 | 0% | |
| Target date for finished first draft | Not Started | 8/13/21 | 8/16/21 | 0% | |
| First round of internal review and edits | Not Started | 8/16/21 | 8/27/21 | 0% | |
| Incorporate edits and prepare review draft | Not Started | 8/30/21 | 9/3/21 | 0% | |
| Draft review by Program Managers | Not Started | 9/7/21 | 9/17/21 | 0% | |
| Incorporate edits and prepare revised draft | Not Started | 9/20/21 | 10/1/21 | 0% | |
| Complete proposed final report and recommendations | Not Started | 10/1/21 | 10/1/21 | 0% | |
| Program "fatal flaw only" review | Not Started | 10/4/21 | 10/8/21 | 0% | |
| Submit final draft for Gov Relations review | Not Started | 10/11/21 | 10/11/21 | 0% | |
| Government Relation review | Not Started | 10/11/21 | 10/29/21 | 0% | |
| Make Government Relations-requested edits | Not Started | 11/1/21 | 11/5/21 | 0% | |
| Submit final for Executive review | Not Started | 11/8/21 | 11/8/21 | 0% | |
| Executive review | Not Started | 11/8/21 | 11/29/21 | 0% | |
| Make any final edits from Executive review | Not Started | 11/29/21 | 11/30/21 | 0% | |
| Submit final report and recommendations (and bill language, if applicable) to Legislature | Not Started | 12/1/21 | 12/1/21 | 0% |