Appendix III
Construction
Environmental
Management Plan
(CEMP)
Environmental Impact Assessment Report (EIAR) Volume 4 of 4
Appendices
Contents
Appendix III: Construction Environmental Management Plan ........................................................................ 1
5.1 Construction Environmental Management Plan ................................................................................. 1
5.2 Construction Traffic Management Plan ............................................................................................ 30
5.3 Invasive Species Management Plan ................................................................................................ 41
5.4 Surface Water Management Plan .................................................................................................... 57
5.5 Construction and Demolition Resource and Waste Management Plan ........................................... 65
5.6 Environmental Incident Response Plan ........................................................................................... 76
5.7 References ....................................................................................................................................... 82
Blanchardstown to City Centre Core Bus Corridor Scheme
Environmental Impact Assessment Report (EIAR) Volume 4 of 4
Appendices
Appendix III: Construction Environmental Management Plan
5.1 Construction Environmental Management Plan
5.1.1 Introduction
This document is the Construction Environmental Management Plan (CEMP) for the Blanchardstown to City
Centre Core Bus Corridor Scheme, hereafter referred to as the Proposed Scheme.
The CEMP will be updated by the National Transport Authority (NTA) (the Employer for the construction works)
prior to the commencement of the Construction Phase, so as to include any additional measures required
pursuant to conditions attached to any decision to grant approval. The NTA shall set out the Employer’s
Requirements in the Construction Contract including all applicable mitigation measures identified in this EIAR, as
well as additional measures required pursuant to conditions attached to any decision to grant approval.
The CEMP comprises the construction mitigation measures, which are set out in the Environmental Impact
Assessment Report (EIAR), and the Natura Impact Statement (NIS), and will be updated to include any additional
measures required pursuant to conditions attached to An Bord Pleanála’s decision.
The CEMP will need to be altered during the lifecycle of the Construction Phase to take account of monitoring
results, permits, legislative changes, outcomes of third-party consultations etc. The appointed contractor will
ensure that the CEMP remains up to date for the duration of the Construction Phase. The appointed contractor
may propose modifications to the CEMP. However, any such modifications, will not give rise to any impacts which
are more significant than those already identified and assessed in the EIAR or NIS.
All of the measures set out in this CEMP will be implemented in full by the appointed contractor and its finalisation
will not affect the robustness and adequacy of the information presented and relied upon in the EIAR and NIS.
5.1.1.1 Purpose
The purpose of the CEMP is to set out the management framework for the delivery of the proposed construction
works and to illustrate how the Proposed Scheme could be delivered in a logical, sensible, and safe sequence
with the incorporation of specific Environmental Commitments, as set out in Section 5.1.9.
The CEMP will be used by the appointed contractor, and the appointed contractor personnel as a guidance
document for the Construction Phase of the Proposed Scheme outlining procedures for the delivery of
environmental mitigation measures and for addressing general day-to-day environmental issues that could arise
during the Construction Phase of the Proposed Scheme.
5.1.1.2 Reference Documents
The CEMP has been prepared as part of the EIAR and the NIS, and should be read in conjunction with the
following Proposed Scheme specific documents:
• The EIAR, with particular reference to Chapter 5 (Construction) in Volume 2 of the EIAR;
• The NIS;
• The Construction Contract; and
• Copies of An Bord Pleanála’s Order, Inspector’s Report and associated documentation.
The appointed contractor will need to comply with all relevant environmental legislation and take account of
published standards, accepted industry practice, national guidelines, and codes of best practice appropriate to
the Proposed Scheme. The CEMP has been prepared in accordance with the following industry best practice
guidance:
• Transport Infrastructure Ireland(TII) (formerly the National Roads Authority (NRA)) Guidelines for
the Creation, Implementation and Maintenance of an Environmental Operating Plan (hereafter
referred to as the TII Guidelines) (TII 2007); and
Blanchardstown to City Centre Core Bus Corridor Scheme Appendix A5.1 Page 1
Environmental Impact Assessment Report (EIAR) Volume 4 of 4
Appendices
• Construction Industry Research and Information Association (CIRIA) in the UK, Environmental Good
Practice on Site Guide, 4th Edition (CIRIA 2015).
5.1.1.3 Scope
This CEMP defines the approach to environmental management implementation. Compliance with the CEMP,
the procedures, work practices and controls will be adhered to by all personnel employed during the Construction
Phase of the Proposed Scheme.
Table 5.1 provides the contents of the CEMP, and where details can be found in this document.
Table 5.1: CEMP Contents
Content Section of CEMP
Introduction 5.1.1
Proposed Scheme Details 5.1.2
Planning Consent 5.1.3
Contact Sheets 5.1.4
Roles and Responsibilities 5.1.5
Communications 5.1.6
Environmental Awareness Training 5.1.7
Compliance and Review 5.1.8
Environmental Commitments 5.1.9
Construction Traffic Management Plan 5.2
Invasive Species Management Plan 5.3
Surface Water Management Plan 5.4
Construction and Demolition Resource and Waste Management Plan 5.5
Environmental Incident Response Plan 5.6
5.1.2 Proposed Scheme Details
Information on the Proposed Scheme will be included in this Section of the CEMP. This information will assist
those without detailed knowledge of the Proposed Scheme in quickly familiarising themselves with the key
elements of the Proposed Scheme and will also assist those who have a need to examine, review or audit the
CEMP.
Details will include a description of the key elements of the Proposed Scheme, an overview of the main works
required at each section, the construction programme, construction methodology, construction plant and
equipment requirements, details on the Construction Compounds, construction traffic management measures,
and interfaces with other projects.
[NTA / appointed contractor shall insert Proposed Scheme details].
5.1.3 Planning Consent
If planning permission is granted for the Proposed Scheme, the entire contents of the planning consent will be
inserted at this location.
[NTA / appointed contractor shall insert planning consent details].
5.1.4 Contact Sheets
Contact details of relevant personnel are required to ensure the efficient reporting of environmental incidents. It
is essential that these contact details be frequently reviewed to ensure they are up to date. Contact details will
include the organisation, position title, name, mobile phone number and email address of relevant personnel.