environmental management plan for proposed api intermediate manufacturing unit located at plot no f 17 midc chincholi solapur maharashtra india project proponent m s livia life sciences pvt ltd environmental ...

icon picture PDF Filetype PDF | Posted on 19 Aug 2022 | 3 years ago
Partial capture of text on file.
                              
              Environmental Management Plan 
           For Proposed API & Intermediate Manufacturing Unit  
                          located at  
        “Plot No. F-17, MIDC Chincholi, Solapur Maharashtra, India” 
                                                      
                              
                       Project Proponent 
                 “M/s Livia Life Sciences Pvt. Ltd.” 
                              
                              
                              
                              
                              
                    Environmental Consultant  
                                  
                    ENVIRO RESOURCES 
               (NABET Certificate No: NABET/EIA/1821/IA0038) 
               E-604 Crystal Plaza, New Link Road, Andheri West, 
                     Mumbai 400053, Maharashtra  
             E-mail: 
                 info@enviroresources.in, Telephone: +91 9867898844 
                              
                              
                              
                                                      
                              
                             Environmental Management Plan – Manufacture of API & Intermediate Products 
                           at Plot No. F-17, MIDC Chincholi, Maharashtra by M/s Livia Life Sciences Pvt. Ltd. 
                                                          TABLE OF CONTENTS 
                   1.      Introduction ........................................................................................................................... 2 
                   2.      Objectives of the EMP........................................................................................................... 2 
                   3.      Environmental Management Plan (EMP) ............................................................................. 3 
                   4.      Greenbelt Development Plan ............................................................................................... 15 
                   5.      Rainwater Harvesting System ............................................................................................. 17 
                   6.      Storm Water Management ................................................................................................... 18 
                   7.      Budgetary Allocation For Environment Protection ............................................................. 20 
                   8.      Corporate Environment Responsibility (CER) Activities ................................................... 21 
                                                                                  
                                                                LIST OF TABLES 
                   Table 1: Anticipated Impacts and Mitigation Measures ................................................................. 4 
                   Table 2: Environmental Management Plan ................................................................................... 10 
                   Table 3: Details of proposed Greenbelt ........................................................................................ 15 
                   Table 4: Estimated Budgetary Expenditure for Plantation ........................................................... 16 
                   Table 5: Capital & Recurring Cost for Green Belt ....................................................................... 17 
                   Table 6: List of Plants Suggested For Green Belt......................................................................... 17 
                   Table 7: Funds for Environmental Management Plan .................................................................. 20 
                   Table 8: CER Action Plan ............................................................................................................. 22 
                   Prepared by M/s Enviro Resources                                                                                  Page 1 
                    
                            Environmental Management Plan – Manufacture of API & Intermediate Products 
                          at Plot No. F-17, MIDC Chincholi, Maharashtra by M/s Livia Life Sciences Pvt. Ltd. 
                                                                  ENVIRONMENTAL MANAGEMENT PLAN 
                   1.       INTRODUCTION 
                   Every industrial development is associated with the positive and negative impacts on 
                   environmental components. Though the probable negative impacts cannot be nullified 
                   completely the much required developmental activities cannot be impeded. 
                   Environmental Impact Assessment helps in identifying potential environmental impacts of a 
                   proposed project activity. Based on the finding of the impact assessment, Environment 
                   Management Plan is devised to minimize the adverse impacts and enumerate various steps to be 
                   taken for improvement of the environment. Environmental Management Plan helps in 
                   formulation, implementation and monitoring of environmental parameters during & 
                   commissioning of project. Environment Management Plan (EMP) is the tool to ensure a safe and 
                   clean environment. A project may have identified proper mitigation measures but without a 
                   management plan to execute it, the desired results may not be obtained. The Environment 
                   Management Plan envisages proper implementation of mitigation measures to reduce the 
                   adverse impacts arising out of the project activities. 
                   2.       OBJECTIVES OF THE EMP 
                   The main objective of Environmental Management Plan is to warrant that the industrial 
                   development in an identified particular study area needs to be entangled with judicious 
                   utilization of non-renewable resources and to ensure that the stress / load on the ecosystem is 
                   within its permissible assimilative capacity i.e. its carrying capacity. In above context 
                   assimilative capacity refers to the maximum amount of pollution load that can be discharged into 
                   the environment without affecting the designated use of various environmental attributes and is 
                   governed by dilution, dispersion and removal due to physico-chemical and biological process. 
                   An effective EMP ensures that these environmental requirements and objectives are satisfied 
                   during all phases of project. The long-term objectives of the EMP for all the environmental 
                   attributes are as under:  
                   •  To comply with all the regulations / applicable laws stipulated by Central & State Pollution 
                      Control Boards. 
                   •  To create good working conditions (devoid of air and noise pollution) for the employees 
                   •  To rationalize and streamline environmental activities to add value in efficiency and 
                      effectiveness 
                   •  To encourage and achieve highest performance and response from individual employees and 
                      contractors 
                   •  To plan out the complete strategy to take care of stakeholder engagement 
                   •  Perspective budgeting and allocation of funds for environment management expenditure 
                   •  To encourage support and conduct developmental works for the purpose of achieving 
                      environment standards and to improve methods of environment management 
                   •  Continuous development and search for innovative technologies for a cleaner and better 
                      environment 
                   Prepared by M/s Enviro Resources                                                                            Page 2 
                    
                            Environmental Management Plan – Manufacture of API & Intermediate Products 
                          at Plot No. F-17, MIDC Chincholi, Maharashtra by M/s Livia Life Sciences Pvt. Ltd. 
                   •  To contribute significantly for sustainable development 
                   •  To prepare a schedule for monitoring and compliance 
                   •  To  establish a watchdog committee voluntarily with an ultimate aim to get ISO 14000 
                      certification 
                   3.       ENVIRONMENTAL MANAGEMENT PLAN (EMP) 
                   To draw a rigid EMP is especially important for us because India has to support 16.1% of the 
                   world’s population only on 2.3% of the global area with 0.4% only of energy reserve. In this 
                   respect, efforts are oriented towards: 
                    
                   •    Effluent of moderate BOD is aerobically treated and used for gardening and reuse in the 
                        manufacturing process for cooling tower makeup. 
                   •    Sober effluent remaining after the process is further used to derive carbon source in form of 
                        Compost, useful on-site and remaining, if any, for the community. 
                         
                   The anticipated impacts and mitigation measures during construction and operation phases has 
                   been chalked out for the various environmental attributes viz, Air, Water, Land, Noise, Ecology, 
                   Socio-economic etc. and the same is presented below in Table 1. 
                    
                   The EMP for the proposed project based on the anticipated impacts and mitigation measures is 
                   as presented in Table 2. 
                    
                   Prepared by M/s Enviro Resources                                                                            Page 3 
                    
The words contained in this file might help you see if this file matches what you are looking for:

...Environmental management plan for proposed api intermediate manufacturing unit located at plot no f midc chincholi solapur maharashtra india project proponent m s livia life sciences pvt ltd consultant enviro resources nabet certificate eia ia e crystal plaza new link road andheri west mumbai mail info enviroresources in telephone manufacture of products by table contents introduction objectives the emp greenbelt development rainwater harvesting system storm water budgetary allocation environment protection corporate responsibility cer activities list tables anticipated impacts and mitigation measures details estimated expenditure plantation capital recurring cost green belt plants suggested funds action prepared page every industrial is associated with positive negative on components though probable cannot be nullified completely much required developmental impeded impact assessment helps identifying potential a activity based finding devised to minimize adverse enumerate various step...

no reviews yet
Please Login to review.