471x Filetype PDF File size 2.57 MB Source: www.afdb.org
REPUBLIC OF ZAMBIA
MINISTRY OF AGRICULTURE
Agriculture Productivity and Market Enhancement Project (APMEP)
ENVIRONMENTAL PROJECT BRIEF
FOR
PROPOSED CONSTRUCTION AND OPERATION OF NJAVIA
IRRIGATION SCHEME IN RUFUNSA DISTRICT
Submitted to: The Zambia Environmental Management Agency
Corner of Suez & Church Roads,
P. O. Box 35131,
LUSAKA, Zambia.
Submitted by: APMEP
Lusaka
@ April 2019
1
EPB – Proposed Irrigation Project
CONTACTS DETAILS
PROJECT PROPONENT: The Ministry of Agriculture
Agriculture Productivity and Market Enhancement Project
(APMEP)
Plot No. 13
Reedbuck Road
Kabulonga
P O Box 50197,
LUSAKA, Zambia
.
CONTACT PERSON: The APMEP Project Coordinator-
Telephone: +260-975 577 365
2
EPB – Proposed Irrigation Project
TABLE OF CONTENTS
Description Page Number
ABBREVIATIONS AND ACRONYMS .............................................................................. 7
EXECUTIVE SUMMARY ............................................................................. 8
1. INTRODUCTION ............................................................................ 16
1.1 PROJECT PROPONENT: AGRICULTURE PRODUCTIVITY AND MARKET
ENHANCEMENT PROJECT (APMEP) .............................................................. 16
1.2 PROJECT INVESTMENT ................................................................................... 16
1.3 TRACK RECORD/ EXPERIENCE...................................................................... 17
1.4 SCOPE OF STUDY ............................................................................................... 17
1.5 STUDY METHODOLOGY .................................................................................. 17
1.6 OBJECTIVES OF THE PROJECT ....................................................................... 18
1.7 SCHEDULE AND LIFE TIME OF THE PROJECT ............................................ 18
2. LEGAL AND POLICY FRAMEWORK ................................................ 19
2.1 THE ENVIRONMENTAL MANAGEMENT ACT NO 12 OF 2011 ................. 19
2.1.1 Statutory Instrument No. 112 of 2013 of Environmental
Management (Licensing) Regulations ........................................................ 19
2.1.2 Statutory Instrument No 28 of 1997, environmental Impact
Assessment (EIA) Regulations. .................................................................. 19
2.2 EMPLOYMENT (AMENDMENT) ACT NO.15 OF 2015 ............................... 20
2.3 THE PETROLEUM ACT CAP 439 AND THE ENERGY REGULATION ACT
CAP 436, 1995 ................................................................................................... 20
2.4 PUBLIC HEALTH ACT CAP 295 OF 1978 ..................................................... 21
2.5 LOCAL GOVERNMENT ACT, 1991 .................................................................. 21
2.6 URBAN AND REGIONAL PLANNING ACT, 2015 .................................. 21
2.7 THE FORESTS ACT NO. 4 OF 2015 ................................................................. 22
2.8 THE WORKERS' COMPENSATION ACT NO. 10 OF 1999 .......................... 22
2.9 THE OCCUPATIONAL HEALTH AND SAFETY ACT NO. 36 OF 2010 ....... 23
2.10 BIO-SAFETY ACT ............................................................................................... 23
2.11 WATER RESOURCE MANAGEMENT ACT, 2011 .......................................... 23
2.12 THE NATIONAL HERITAGE CONSERVATION COMMISSION ACT CAP 173
OF 1989 ................................................................................................................ 24
2.13 THE CHIEFS ACT 13 OF 1994 ......................................................................... 24
2.14 AGRICULTURE LANDS ACT OF 1960 ............................................................ 25
2.15 NOXIOUS WEEDS ACT CAP 231 ..................................................................... 25
2.16 THE LAND SURVEY ACT, 1960 ....................................................................... 25
2.17 INTERNATIONAL CONVENTIONS AND PROTOCOLS ................................ 26
2.17.1 The Basel Convention on the Control of Transboundary movements
of Hazardous wastes and their disposal ...................................................... 26
2.17.2 Montreal Protocol on Substances that deplete the ozone layer. ..... 26
2.17.3 Convention Concerning the Protection of the World Cultural and
Natural Heritage .......................................................................................... 27
2.18 INSTITUTIONAL FRAMEWORK ..................................................................... 27
3. PROJECT DESCRIPTION ................................................................ 29
3.1 LOCATION ............................................................................................................... 29
3
EPB – Proposed Irrigation Project
3.2 NATURE OF THE PROJECT ....................................................................................... 31
3.2.1 Activities and technology ................................................................... 31
3.2.2 RAW MATERIALS ............................................................................. 34
3.2.3 Products and by- Products ................................................................ 35
3.2.4 Schedule and life time of the project ................................................. 36
3.3 MAIN ACTIVITIES ................................................................................................... 36
3.3.1 SITE PREPARATION PHASE ........................................................... 36
3.3.2 CONSTRUCTION/INSTALLATION PHASE ..................................... 36
3.3.3 OPERATION PHASE ........................................................................ 36
4. PROJECT ALTERNATIVES .............................................................. 37
4.1 SITE ALTERNATIVES ........................................................................................ 37
4.2 IRRIGATION METHODS ALTERNATIVES .................................................... 37
4.3 PIPELINE MATERIALS ALTERNATIVE ......................................................... 38
4.4 WASTE WATER DISPOSAL ALTERNATIVES ............................................... 38
4.5 FARMING METHODS ........................................................................................ 38
4.6 ENERGY SOURCE ALTERNATIVES ............................................................................ 38
4.7 DO NOTHING OPTION ...................................................................................... 39
5. DESCRIPTION OF THE BASELINE ENVIRONMENT ........................ 40
5.1 ECOLOGICAL RESOURCES ........................................................................................ 40
A. FAUNA .................................................................................................................... 40
B. FLORA ........................................................................................................................... 41
5.2 TOPOGRAPHY ......................................................................................................... 41
5.3 GEOLOGY AND SOILS .............................................................................................. 41
5.4 CLIMATE ................................................................................................................. 41
5.5 HYDROLOGY ........................................................................................................... 42
5.6 AIR QUALITY AND NOISE ........................................................................................ 42
5.7 LAND USE ............................................................................................................... 42
5.8 SOCIO-ECONOMIC ENVIRONMENT .............................................................. 42
5.8.1 Rufunsa District ................................................................................. 42
5.8.2 Economic Activities .......................................................................... 42
5.8.3 Land Tenure ....................................................................................... 42
5.8.4 Archaeological and Cultural Sites .................................................... 43
5.8.5 Population and Settlement ............................................................... 43
5.8.6 Health Facilities................................................................................ 43
6. ENVIRONMENTAL IMPACTS .......................................................... 45
6.1 POSITIVE IMPACTS ................................................................................................. 45
6.1.1 Anticipated Positive Socio-Economic Impacts .................................. 45
6.1.2 Anticipated Positive Bio-Physical Environmental Impacts ............... 46
6.2 NEGATIVE IMPACTS ................................................................................................ 46
6.2.1 CONSTRUCTION PHASE .............................................................. 46
6.2.2 OPERATION PHASE ...................................................................... 50
6.3 METHODOLOGY OF IMPACT EVALUATION .............................................................. 55
6.3.1 Impacts Evaluation Procedure ......................................................... 55
6.3.2 Assessment and Ranking of identified Impacts ............................... 58
7. ENVIRONMENTAL SOCIAL MANAGEMENT PLAN .......................... 64
7.1 SUMMARY OF ENVIRONMENTAL MANAGEMENT PLAN ......................... 66
4
no reviews yet