Project Feasibility Analysis
• For me it all started with a term paper
–Ice Plant article by Richardson and Mapp,
Southern Journal of Agricultural Economics
(SJAE) 1976 – used risk for feasibility
analysis
–The article demonstrated the methodology
for risk based feasibility studies, and it was
first to report
• Probability of Economic Success
• Probabilistic Cash Flows to meet cash needs
• Financial/Economic analyses have been
used hundreds of times for a wide
variety of firm based problems
Project Feasibility Analysis
• In business most feasibility studies use
Excel spreadsheet models
– This trend by business started in mid-90s
– Excel is the language of business analysis
• Feasibility studies generally ignore risk –
many do a “What if …” study for the Best
Case and Worst Case scenarios
• Some analysts think they considered risk
by including a 10 year “average” price
• Excel deterministic feasibility models are
easily converted to stochastic feasibility
models
– Just make the forecasted variables stochastic
using the residuals from the forecast models
Project Feasibility Analysis
• Risks to consider for a feasibility
analysis are:
– Price of raw inputs, as fuel and labor
– Price of the product or output
– Production risk
– Black Swan events
– Competition and market share over the life
of investment (business)
– Cost of the plant and product development
– Cost of production for the finished product
• Project feasibility is where we put it all
together in an analysis of Time, Money,
and Economic Viability
Project Feasibility Analysis
• Project Feasibility: consider the Time, Money
(Cost), and Economic Viability of the finished
business
• Simulate the Time to complete or build the
plant
• Simulate the Cost of developing the plant
incorporating risk into the plant’s development
costs PP((T)T)
PPrroojejecct t
• MMaannaaggeemmeenntt
Simulate the Economic Viability of the
completed plant (business) TTiimmee
PP((CC))
Bid
AAnnaallysisysis
CCoosstt ((mmoonneey)y)
P( )
P( )
PPrroojejectct
FFeeaasibsibiilitylity
RRaattee ooff RReettuurrnn
Project Feasibility Analysis
• Proposed business with a new product
• Tasks and duration/costs
Tasks Description Time (mo.) Costs ($1,000)
1 Plant Modification3-5 300-325
2 Product Development 1-3 200-300
3 Distribution System 2-3 50-100
4 Marketing Program 3-4 100-150
• Finance 100% of project costs @ 9%
• Marginal cost of production/unit Uniform(10,15), a scenario
variable
• Fixed Costs/year $200,000
• Inflation Uniform(0.04, 0.05) percent per year
• Demand Projections
Years Price/Unit Quantity Sold/Year
1-3 U(13.5,14) U(500K, 600K)
4-5 U(13,13.5) U(400K, 500K)
6-10 U(12.5,13) U(300K, 400K)