Practice Problems
Practice Problems
Problem 1:
The following represent activities in a major construction project. Draw the
network to represent this project.
Activity Immediate Predecessor
A —
B —
C A
D B
E B
F C, E
G D
H F, G
PowerPoint presentation to accompany Heizer/Render – 3-2 © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458
Principles of Operations Management, 5e, and Operations
Management, 7e
Practice Problems
Practice Problems
Problem 2:
Given the following Time Chart and Network Diagram, find the Critical Path.
Activity a m b t Variance Activity C
t = 6
A 2 3 4 3 1/9
B 1 2 3 2 1/9 Activity A Activity E
C 4 5 12 6 16/9 t = 3 t = 2
D 1 3 5 3 4/9 Activity D
E 1 2 3 2 1/9 t = 3
Activity B
t = 2
PowerPoint presentation to accompany Heizer/Render – 3-3 © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458
Principles of Operations Management, 5e, and Operations
Management, 7e
Practice Problems
Practice Problems
Problem 2:
Given the following Time Chart and Network Diagram, find the Critical Path.
Activity a m b t Variance Activity C
t = 6
A 2 3 4 3 1/9
B 1 2 3 2 1/9 Activity A Activity E
C 4 5 12 6 16/9 t = 3 t = 2
D 1 3 5 3 4/9 Activity D
E 1 2 3 2 1/9 t = 3
Activity B
t = 2
Critical Path
PowerPoint presentation to accompany Heizer/Render – 3-4 © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458
Principles of Operations Management, 5e, and Operations
Management, 7e
Practice Problems
Practice Problems
Problem 3:
What is the variance in completion time for the
critical path found in Problem 2?
Activity a m b t Variance Activity C
t = 6
A 2 3 4 3 1/9
B 1 2 3 2 1/9 Activity A Activity E
C 4 5 12 6 16/9 t = 3 t = 2
D 1 3 5 3 4/9 Activity D
E 1 2 3 2 1/9 t = 3
Activity B
t = 2
Critical Path
PowerPoint presentation to accompany Heizer/Render – 3-5 © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458
Principles of Operations Management, 5e, and Operations
Management, 7e
Total variance = variances of activities on critical path
Practice Problems
Practice Problems
Problem 3:
Total variance = 1/9 + 16/9 + 4/9 + 1/9 = 23/9 = 2.56
23 23 4.796
What is the variance in completion time for the
And = = = = 1.6 and 2.56 = 1.6
9 3 3
critical path found in Problem 2?
Activity a m b t Variance Activity C
t = 6
A 2 3 4 3 1/9
B 1 2 3 2 1/9 Activity A Activity E
C 4 5 12 6 16/9 t = 3 t = 2
D 1 3 5 3 4/9 Activity D
E 1 2 3 2 1/9 t = 3
Activity B
t = 2
Critical Path
PowerPoint presentation to accompany Heizer/Render – 3-6 © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458
Principles of Operations Management, 5e, and Operations
Management, 7e
no reviews yet
Please Login to review.