LECTURE 4
CPM Analysis for AOA
FERDINAND FASSA
OUTLINE LECTURE 4
• REVIEW LECTURE 3
• INTRODUCTION CPM
• Calculating the Critical Path
Terminology CPM
• Critical - Activities, events, or paths which, IF
DELAYED, WILL DELAY THE COMPLETION OF THE
PROJECT. A project’s critical path is understood to
mean that sequence of critical activities that connect
the project’s start event to its finish event
• Path - The series of connected activities (or
intermediate events) between any two events in a
network or
• Path - Any route along the network from start to finish
Critical Path Method
Critical Path – path with the longest total duration
This is the shortest time in which the project can be completed.
Critical Activity – an activity on the critical path
*If a critical activity is delayed, the entire project will be
delayed. Close attention must be given to critical
activities to prevent project delay. There may be
more than one critical path.
CPM is a network diagramming technique used to
PREDICT TOTAL PROJECT DURATION.