CROW
5.25.0.236
Member Test Kick-Off Meeting
2
Agenda
• Objectives
• Testing Timeline
• CROW 5.25.0.236 Overview
• Test Checklist
• Test Environment
• Expectations
• RMS
• Reference Material
• Recap
• Questions
3
Objectives
• Meeting Objectives
Provide an overview of the CROW 5.25.0.236
Provide a review of the testing schedule
Outline responsibilities of CROW users and SPP
project team
Address questions from the participants
• Testing Objectives
Provide CROW users hands-on experience with
the updates and changes that are contained in
the CROW 5.25.0.236 prior to Production
Implementation
Ensure changes are functioning as designed and
requested
4
Test Timelines
• Oct 28 – Member Test Checklist published to
CWG Project folder
• Nov 4 – Member Test Kick-Off Meeting
• Nov 11 – Start of Member Testing in MTE
• Jan 13 – End of Test Period
• Jan 13 – Last day to return a Test Checklists
to SPP
• Feb 3 – Production Go-Live
5
CROW 5.25.0.236 Overview
• The CROW 5.25.0.236 project is undertaken
to correct defects related to equipment no
longer being listed in the subject line of
email and the inability to update outage
profiles through the API. An enhancement
associated with the release is the ability to
submit overlapping generation rules.
• No software or process changes are
expected for members to be able to
continue using CROW.
• Only Asset Owning MPs and Transmission
Operators may participate in the Test.
6